Approval for Expansion of Cinsa 66 kV Substation in Gran Canaria
Published: June 17, 2026|environment-and-sustainability|Gobierno de Canarias
Infrastructure Expansion in the Canary Islands
Project Overview
The Canary Islands government has approved plans to expand the Cinsa 66 kV substation in Telde, Gran Canaria, a move vital for strengthening the local electricity network.
- Red ElƩctrica de EspaƱa submitted the request in November 2025, aiming to add a new emergency generation installation to improve grid resilience.
- After a public consultation period and various approvals from regional authorities, the project received favorable reports from the Gran Canaria Cabildo and the national EcoTransition Ministry.
- Notably, Teldeās local council did not respond within the legal deadline, which is legally deemed as approval.
Alignment with National Energy Goals
This expansion aligns with Spainās broader energy development plan (2021-2026), prioritizing a reliable and resilient electricity supply for residents.
"The project helps ensure users have access to high-quality power, supporting both household and industrial needs," the government emphasizes.
Regulatory and Construction Details
- Construction must adhere to technical regulations.
- The project is exempt from local licensing, simplifying the process.
Conditions and Safety Measures
The approval includes conditions to ensure safety, proper execution, and transparency:
- The developer will need to provide guarantees before starting work.
- The developer must follow safety rules during construction.
Significance
This infrastructure upgrade is a clear step towards modernizing the Canary Islandsā energy grid, boosting energy security, and supporting renewable integration in the region.